Coles Wind Road work for 4/9/26
Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.Scheduled work subject to change due to weather/site conditions.
OVERNIGHT CLOSURE on 1700E from 1900N to 1800N due to open trench. Road closed to thru traffic on 1500N from IL-130 to 1100E until 4/27/26. Road closed on 1500N from IL-130 to 1700E for culvert install C-33 and I-139. Road closed on 1400N from 1300E to 1400E for culvert install C-07 and I-167. Road closed on 1400E from 1700N to 1600N for placing blister patches. Road closed on 1600N from IL-130 to 1400E for placing blister patches. Road closed on 1700N from IL-130 to 1900E for trenching. Road closed on 1700N from IL-130 to 1300E for placing dirt embankment. Road closed on 1800N from IL-130 to 1700E for trenching and agg base widening. Flagmen will be used for any short-term partial lane closures while prepping for future culvert installs.
Dirtworks will continue trenching and installing culverts.
Dunn Company will continue cement stabilization and pre pulverization.
Coles Wind Road work for 4/8/26
Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.Scheduled work subject to change due to weather/site conditions.
Road closed to thru traffic 1500N from IL-130 to 1100E until 4-27-26. Road closed on 1900N from IL-130 to 1400E for culvert install C-76 and A-5.
Road closed on 1500E from 1800N to 100N for culvert install C-76 and A-5. Road closed on 1400E from 1600N to 1500N for culvert install C-139 and I-174.
Road closed on 1800N from IL-130 to 1820E for trenching and agg base widening. Road closed 1820 from 1800n to 1600N for agg base widening.
Road closed on 1700N from 1300E to 1900E for placing dirt embankment and trenching. Road closed on1700E from 1900N to 1800N for trenching.
Road closed on 1400E from 1700N to 1400N for placing blister patches. Road closed on 1600N from IL-130 to 1300E for placing blister patches.
Flagmen will be used for any short-term partial closures while prepping for future culvert installs.
Coles Wind Road work for 4/7/26
Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.Scheduled work subject to change due to weather/site conditions.
Road closed to thru traffic on 1500N from IL-130 to 1100E until 4/27/26. Road closed on 1900N from IL-130 to 1400E for culvert install C-77 and I-188. Road closed on 1500E from 1700N to 100N for culvert install C-77 and I-188. Road closed on 1800N from IL-130 to 1300E for culvert install C-143 and A-20. Road closed on 1400E from 1900N to 1700N for culvert install C-143 and A-20. Road closed on 1700N from IL-130 to 1400E to lay 2-4” add rock. Road closed on 1820E from 1800N to 1700N for trenching. Road closed on 1800N from 1300E to 1820E for trenching. Road closed on 1700E from 1900N to 1800N for trenching. Road closed on 1300E from 1500N to 1400N for placing dirt embankment. Road closed on 1500E from 1400N to 1200N for placing dirt embankment. Road closed on 1400N from IL-130 to 1300E for placing dirt embankment. Flagmen will be used for any short-term partial lane closures while prepping for future culvert installs.
Crews will continue trenching and installing culverts.
Dunn Company will start pre pulverization and continue milling.
Crews will continue laying add rock, agg base widening, prepping roads for widening, and hauling in rock to the Welcome Center.
Coles Wind Road work for 4/6/26
Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.Scheduled work subject to change due to weather/site conditions.
Road closed to thru traffic on 1500N from IL-130 to 1100E until 4/27/26. Road closed on 1500N from 1800E to 1700E for culvert install I-140 and C-34. Road closed on 1400E from 1700N to 1400N for culvert install C-141 and C-140. Road closed on 1700N from IL-130 to 1300E to lay 2-4” add rock. Road closed on 1820E from 1800N to 1600N for trenching. Road closed on 1800N from 1300E to 1820E for placing dirt embankment and trenching. Road closed on 1400N from IL-130 to 1300E for laying dirt embankment. Flagmen will be used for any short-term partial lane closures while prepping for future culvert installs.
Crews will continue trenching and installing culverts.
Dunn Company will start milling.
Crews will continue laying add rock, agg base widening, prepping roads for widening, and hauling in rock to the Welcome Center.
Thanks,
Coles Wind Road work no work 4-4-26 4-5-26
Notice: Road closed to thru traffic on 1500N from IL-130 to 1100E starting on Monday 4/6/26 and reopening on Monday 4/27/26.
Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Scheduled work subject to change due to weather/site conditions.
No work planned for the weekend
Coles Wind Road work for 4/3/2026
All scheduled work is subject to change due to weather / site conditions
Notice: Road closed to thru traffic on 1500N from IL-130 to 1100E starting on Monday 4/6/26 and reopening on Monday 4/27/26.
4-3-26
Road closed on 1500N from 1800E to 1700E for culvert install C-35 and I-141. Road closed on 1700N from IL-130 to 1500E for culvert install C-114. Road closed on 1700N from 1300E to 1400E for drainage correction at culvert C-107. Road closed on 1800N from 1300E to 1820E for laying dirt embankment and blister culvert patches. Road closed on 1600N from IL-130 to 1820E for trenching and agg base widening. Road closed on 1400N from IL-130 to 1300E for laying dirt embankment. Road closed on 1700N from 1400E to 1500E for laying blister culvert patches. Road closed on 1600N from IL-130 to 1300E to fill culvert crossings. Road closed on 1820E from 1600N to 1700N for trenching. Flagmen will be used for any short-term partial lane closures while prepping for future culvert installs.
Crews will continue trenching and installing culverts.
Crews will continue agg base widening, prepping roads for widening, and hauling in rock to the Welcome Center.
Coles Wind Road work for 4/2/2026
Road closed to thru traffic on 1500N from IL-130 to 1100E starting on Monday 4/6/26 and reopening on Monday 4/27/26
Road closed on 1700N from IL-130 to 1700E for culvert install C-121. Road closed on 1500N from IL-130 to 1500E for culvert install I-136. Road closed on 1700N from IL-130 to 1500E for culvert install C-114. Road closed on 1800N from IL-130 to 1300E to lay 2” add rock. Road closed on 1600N from IL-130 to 1400E for placing dirt embankment. Road closed on 1600N from IL-130 to 1820E for agg base widening. Road closed on 1820E from 1800N to 1600N for trenching. Road closed on 1400N from IL-130 to 1300E for placing dirt embankment. Road closed on 1400E from 1700N to 1400E for placing dirt embankment.
Crews will continue trenching and installing culverts.
Crews will continue laying 2” add rock, continue agg base widening, prepping roads for widening, and hauling in rock to the Welcome Center.
Coles Wind Road work for 4/1/26
Road closed on 1700N from 1500E to 1700E for culvert install C-114 and C-121. Road closed on 1700N from 1300E to 1400E for culvert drainage correction at C-107. Road closed on 1800N from IL-130 to 1300E for laying 2” add rock. Road closed on 1600N from IL-130 to 1820E for agg base widening. Road closed on 1600N from IL-130 to 1400E for adding dirt embankment. Road closed on 1820E from 1800N to 1600N for trenching. Flagmen will be used for any short-term partial lane closures while prepping for future culvert installs.
Crews will continue trenching and installing culverts.
Crews will continue laying 2” add rock, continue agg base widening, prepping roads for widening, and hauling in rock to the Welcome Center.
Thanks,
Coles Wind Road work for 3/31/26
Road closed on 1700N from 1700E to 1820E for culvert install C-122. Road closed on 1700N from IL-130 to 1400E for culvert install C-110, C-114. Road closed on 1600N from 1300E to 1820E for placing dirt embankment. Road closed on 1500E from 1400N to 1200N for agg base widening. Road closed on 1400N from IL-130 to 1300E for agg base widening and trenching. Road closed on 1300E from 1500N to 1400N for trenching and agg base widening. Road closed on 1400E from 1700N to 1400N for placing dirt embankment. Road closed on 1800N from IL-130 to 1300E for 2” add rock. Flagmen will be used for any short-term partial lane closures while prepping for future culvert installs.
Dirtworks will continue trenching and installing culverts.
Evergreen will start laying 2” add rock, continue agg base widening, prepping roads for widening, and hauling in rock to the Welcome Center
Coles Wind Road work for 3/30/26
Road closed on 1700N from IL-130 to 1820E for culvert install C-121, C-122, C-123. Road closed on 1700N from 1300E to 1400E for culvert install C-108, C-109. Road closed on 1600N from 1300E to 1820E for agg base widening. Road closed on 1400E from 1700N to 1400N for agg base widening and adding dirt embankment. Road closed on 1500E from 1400N to 1200N for agg base widening. Road closed on 1400N from IL-130 to 1300E for trenching. Road closed on 1300E from 1400N to 1500N for trenching. Soft road closure on 1900N from IL-130 to 1400E for adding dirt embankment. Flagmen will be used for any short-term partial lane closures while prepping for future culvert installs.
Crews will continue trenching and installing culverts.C
Crews will continue agg base widening, prepping roads for widening, and hauling in rock to the Welcome Center