Coles Wind Road work for 7/12/26
Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.Scheduled work subject to change due to weather/site conditions
Monday: Road closed on 1400N from 1300E to IL-130 until 7/13/26 for laying oil and chip. Road closed on 1400E from 1600N to 1300N until 7/17/26 for spraying prime coat and laying A-1 oil and chip . Road closed on 1500E from 1500N to 1200N until 7/13/26 for laying oil and chip. Flagmen will be used for any short term road partial lane closures.
Evergreen will continue laying A-1 oil and chip and dirt embankment. Thanks,
Coles Wind Road work for 7/11/26
Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.Scheduled work subject to change due to weather/site conditions.
Saturday: Road closed on 1400N from 1300E to IL-130 until 7/13/26 for prime coat cure. Road closed on 1400E from 1600N to 1300N until 7/17/26 for spraying prime coat. Road closed on 1500E from 1500N to 1200N until 7/13/26 for prime coat cure. Flagmen will be used for any short term road partial lane closures.
Monday: Road closed on 1400N from 1300E to IL-130 until 7/13/26 for laying oil and chip. Road closed on 1400E from 1600N to 1300N until 7/17/26 for spraying prime coat and laying A-1 oil and chip . Road closed on 1500E from 1500N to 1200N until 7/13/26 for laying oil and chip. Flagmen will be used for any short term road partial lane closures.
Evergreen will continue laying A-1 oil and chip and dirt embankment. Thanks,
Coles Wind Road work for 7/10/26
Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.Scheduled work subject to change due to weather/site conditions.
Road closed on 1400N from 1300E to IL-130 until 7/13/26 for prime coat cure. Road closed on 1400E from 1600N to 1300N until 7/17/26 for paving 3” agg cap. Road closed on 1500E from 1500N to 1200N until 7/13/26 for prime coat cure. Flagmen will be used for any short term road partial lane closures.
Evergreen will continue paving 3” agg cap and laying dirt embankment. Thanks,
Coles Wind Road work for 7/9/26
Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.Scheduled work subject to change due to weather/site conditions.
Road closed on 1400N from 1300E to IL-130 until 7/13/26 for spraying prime coat. Road closed on 1400E from 1600N to 1300N until 7/17/26 for paving 3” agg cap. Road closed on 1500E from 1500N to 1200N until 7/13/26 for spraying prime coat. Flagmen will be used for any short term road partial lane closures.
Evergreen will continue paving 3” agg cap and spraying prime coat. Thanks,
Coles Wind Road work for 7/8/26
Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.Scheduled work subject to change due to weather/site conditions.
Road closed on 1400N from 1300E to IL-130 until 7/9/26 for spraying prime coat and laying dirt embankment. Road closed on 1400E from 1600N to 1300N until 7/17/26 for cement cure. Road closed on 1500E from 1500N to 1200N until 7/9/26 for spraying prime coat. Road closed on 1300E from 1500N to 1400N for laying dirt embankment. Flagmen will be used for any short term road partial lane closures.
Evergreen will continue laying dirt embankment and spraying prime coat. Thanks,
Coles Wind Road work for 7/7/26
Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.Scheduled work subject to change due to weather/site conditions.
Road closed on 1400N from 1300E to IL-130 until 7/8/26 for paving 3” cap rock. Road closed on 1400E from 1600N to 1300N until 7/8/26 for cement cure. Road closed on 1500E from 1500N to 1200N until 7/8/26 for paving 3” cap rock. Road closed on 1300E from 1500N to 1400N for laying dirt embankment. Flagmen will be used for any short-term road partial lane closures.
Evergreen will continue laying dirt embankment and paving 3” cap rock. Thanks,
Coles Wind Road work for 7/6/26
Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.Scheduled work subject to change due to weather/site conditions.
Road closed on 1400N from 1300E to IL-130 until 7/7/26 for cement cure. Road closed on 1400E from 1600N to 1300N until 7/7/26 for cement cure. Road closed on 1500E from 1500N to 1200N until 7/7/26 for cement cure. Road closed on 1400N from 1800E to 2000E for laying dirt embankment. Road closed on 1850E from 1400N to 1300N for laying dirt embankment. Flagmen will be used for any short term road partial lane closures.
Evergreen will continue laying dirt embankment. Thanks,
Coles Wind Road work for 7/3/26 Thru 7/5/26
There will be no road work beginning Friday thru Sunday 7/5/26
Thank you all for your patience and understanding
Have a great 4th of July
God Bless America.
Coles Wind Road work for 7/2/26
Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.Scheduled work subject to change due to weather/site conditions.
Tower Deliveries, please be patient with the increased traffic.
Road closed on 1500N from IL-130 to 1800E for laying dirt embankment. Road closed on 1800E from 1600N to 1400N for laying dirt embankment. Road closed on 1400N from 1300E to IL-130 until 7/7/26 for cement cure. Road closed on 1400E from 1600N to 1300N until 7/7/26 for cement cure. Road closed on 1500E from 1500N to 1200N until 7/7/26 for cement cure. Flagmen will be used for any short-term road partial lane closures.
Evergreen will continue laying dirt embankment. Thanks,
Coles Wind Road work for 7/1/26
Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.Scheduled work subject to change due to weather/site conditions.
Tower Deliveries, please be patient with the increased traffic.
Road closed on 1500N from IL-130 to 1820E for laying dirt embankment. Road closed on 1820E from 1700N to 1600N for laying dirt embankment. Road closed on 1600N from IL-130 to 1820E for laying dirt embankment. Road closed on 1400N from 1300E to IL-130 until 7/7/26 for cement cure. Road closed on 1400E from 1600N to 1300N until 7/7/26 for cement cure. Road closed on 1500E from 1500N to 1200N until 7/7/26 for cement cure. Flagmen will be used for any short term road partial lane closures.
Evergreen will continue laying dirt embankment. Thanks,