Coles Wind Road work for 6/5/26

Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures. Will be granted access.Scheduled work subject to change due to weather/site conditions. Road closed on 1700N from IL-130 to 2000E until 6/6/26 for spraying prime coat. Road closed on 1820E from 1800N to 1600N until 6/8/26 for spraying prime coat and paving 3” cap rock. Road closed on 1600N from IL-130 to 1875E until 6/8/26 for paving 3” cap rock. Road closed on 1800E from 1600N to 1400N/South street until 6/8/26 for cement cure and pre pulverization. Road closed on 1850E from 1400N to 1300N until 6/12/26 for cement cure. Road closed on 1400N from 1800E to 2000E until 6/12/26 cement cure. Road closed on 1500N from 1700E to 1800E until 6/15/26 for pre pulverization and cement stabilization. Road closed on 1770E from 1400N to 1300N until 6/12/26 for cement cure. Flagmen will be used for any short-term partial lane closures. Dirtworks will continue cleaning culverts. Dunn Company will continue cement stabilization and pre pulverization. Evergreen will continue paving 3” cap rock and spraying prime coat. Thanks,  

Coles Wind Road work for 6/4/26

Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures. Will be granted access.Scheduled work subject to change due to weather/site conditions. Road closed on 1700N from IL-130 to 2000E until 6/6/26 for paving 3” cap rock. Road closed on 1820E from 1800N to 1600N until 6/8/26 for cement cure and paving 3” cap rock. Road closed on 1600N from IL-130 to 1875E until 6/8/26 for cement cure and cement stabilization. Road closed on 1800E from 1500N to 1400N/South street until 6/8/26 for cement cure and pre pulverization. Road closed on 1850E from 1400N to 1300N until 6/12/26 for cement cure. Road closed on 1400N from 1800E to 2000E until 6/12/26 cement stabilization and cement cure. Road closed on 1500N from 1700E to 1800E for pre pulverization. Flagmen will be used for any short-term partial lane closures. Dirtworks will continue cleaning culverts. Dunn Company will continue cement stabilization and pre pulverization. Evergreen will continue paving 3” cap rock and hauling rock to the Welcome Center. Thanks,  

Coles Wind Road work for 6/3/26

Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures. Will be granted access.Scheduled work subject to change due to weather/site conditions. Road closed on 1700N from IL-130 to 2000E until 6/5/26 for placing blister patches and paving 3” cap rock. Road closed on 1820E from 1800N to 1600N until 6/8/26 for cement cure. Road closed on 1600N from IL-130 to 1875E until 6/8/26 for cement cure and cement stabilization. Road closed on 1800E from 1500N to 1600N until 6/8/26 for cement cure and cement stabilization. Road closed on 1850E from 1400N to 1300N until 6/12/26 for pre pulverization and cement stabilization. Road closed on 1400N from 1800E to 2000E until 6/12/26 for pre pulverization and cement stabilization. Flagmen will be used for any short-term partial lane closures. Dirtworks will continue cleaning culverts. Dunn Company will continue cement stabilization and pre pulverization. Evergreen will continue paving 3” cap rock and hauling rock to the Welcome Center.Thanks,  

Coles Wind Road work for 6/2/26

Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures. Will be granted access.Scheduled work subject to change due to weather/site conditions. Road closed on 1700N from IL-130 to 2000E until 6/5/26 for placing blister patches. Road closed on 1800N from IL-130 for laying dirt embankment. Road closed on 1700E from 1900N to 1800N for dirt embankment. Road closed on 1820E from 1900N to 1600N until 6/2/26 for cement cure and laying dirt embankment. Road closed on 1600N from IL-130 to 1875E until 6/8/26 for cement cure and cement stabilization. Road closed on 1800E from 1500N to 1600N until 6/8/26 for cement cure and cement stabilization. Road closed on 1850E from 1400N to 1300N for pre pulverization. Road closed on 1400N from 1800E to 2000E for pre pulverization. Flagmen will be used for any short-term partial lane closures. Dirtworks will continue cleaning culverts. Dunn Company will continue cement stabilization and pre pulverization. Evergreen will continue laying dirt embankment and hauling rock to the Welcome Center. Thanks,  

Coles Wind Road work for 6/1/26

Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures. Will be granted access.Scheduled work subject to change due to weather/site conditions. Road closed on 1700N from IL-130 to 2000E until 6/5/26 for cement cure. Road closed on 1800N from IL-130 for laying dirt embankment. Road closed on 1700E from 1900N to 1800N for dirt embankment. Road closed on 1820E from 1900N to 1600N until 6/2/26 for cement cure and laying dirt embankment. Road closed on 1600N from IL-130 to 1875E until 6/8/26 for cement cure and cement stabilization. Road closed on 1800E from 1500N to 1600N until 6/8/26 for cement cure and cement stabilization. Road closed on 1850E from 1400N to 1300N for pre pulverization. Flagmen will be used for any short-term partial lane closures. Dirtworks will continue cleaning culverts. Dunn Company will continue cement stabilization and pre pulverization. Evergreen will continue laying dirt embankment and hauling rock to the Welcome Center. Thanks,

Coles Wind Road work for 5/30/26

Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures. Will be granted access.Scheduled work subject to change due to weather/site conditions. Road closed on 1700N from IL-130 to 2000E until 6/5/26 for cement cure. Road closed on 1800N from IL-130 for laying oil and chip. Road closed on 1700E from 1900N to 1800N for laying oil and chip. Road closed on 1820E from 1900N to 1600N until 6/2/26 for cement cure and laying oil and chip. Road closed on 1600N from IL-130 to 1875E until 6/8/26 for pre pulverization and cement stabilization. Road closed on 1800E from 1500N to 1600N until 6/8/26 for pre pulverization and cement stabilization. Flagmen will be used for any short-term partial lane closures. Dunn Company will continue cement stabilization and pre pulverization. Evergreen will continue laying A-1 dust control oil and chip. Thanks.  

Coles Wind Road work for 5/29/26

Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures. Will be granted access.Scheduled work subject to change due to weather/site conditions. Road closed on 1700N from IL-130 to 2000E until 6/5/26 for cement stabilization and pre pulverization. Road closed on 1800N from IL-130 to 1950E until 5/30/26 for spraying prime coat. Road closed on 1700E from 1900N to 1800N until 5/30/26 for curing prime coat. Road closed on 1820E from 1900N to 1600N until 6/2/26 for cement stabilization and spraying prime coat.  Road closed on 1600N from IL-130 to 1300E for laying dirt embankment. Road closed on 1400E from 1700N to 1500N for laying dirt embankment. Road closed on 1600N from IL-130 to 1875E until 6/8/26 for pre pulverization and cement stabilization. Road closed on 1800E from 1500N to 1600N until 6/8/26 for pre pulverization and cement stabilization. Flagmen will be used for any short-term partial lane closures. Dirtworks will continue cleaning out culverts. Dunn Company will continue cement stabilization and pre pulverization. Evergreen will continue laying dirt embankment, spraying prime coat, and hauling in rock to the Welcome Center.

Coles Wind Road work for 5/28/26

Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures. Will be granted access.Scheduled work subject to change due to weather/site conditions. Road closed on 1700N from IL-130 to 2000E until 6/5/26 for cement stabilization and pre pulverization. Road closed on 1800N from IL-130 to 1950E until 5/30/26 for laying 3” agg cap. Road closed on 1700E from 1900N to 1800N until 5/30/26 for curing prime coat. Road closed on 1820E from 1900N to 1600N until 6/2/26 for cement cure.  Road closed on 1600N from IL-130 to 1300E for laying dirt embankment. Road closed on 1400E from 1700N to 1500N for laying dirt embankment. Flagmen will be used for any short-term partial lane closures. Dirtworks will continue cleaning out culverts. Dunn Company will continue cement stabilization and pre pulverization. Evergreen will continue laying 3” agg cap and hauling in rock to the Welcome Center.  

Coles Wind Road work for 5/27/26

Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures. Will be granted access.Scheduled work subject to change due to weather/site conditions.   Road closed on 1700N from IL-130 to 2000E until 6/2/26 for cement stabilization and pre pulverization. Road closed on 1800N from IL-130 to 1950E until 5/28/26 for cement cure. Road closed on 1700E from 1900N to 1800N until 5/28/26 for curing prime coat. Road closed on 1820E from 1900N to 1600N until 6/2/26 for cement cure.  Road closed on 1600N from IL-130 to 1300E for laying dirt embankment. Road closed on 1400E from 1700N to 1500N for laying dirt embankment. Flagmen will be used for any short-term partial lane closures. Dirtworks will continue cleaning out culverts. Dunn Company will continue cement stabilization and pre pulverization. Evergreen will continue laying dirt embankment and hauling in rock to the Welcome Center. Thanks,  

RE-Coles Wind Road work for 5/26/26

Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures. Will be granted access.Scheduled work subject to change due to weather/site conditions. Road closed on 1700N from IL-130 to 2000E until 6/2/26 for cement stabilization and pre pulverization. Road closed on 1800N from IL-130 to 1950E until 5/28/26 for cement cure. Road closed on 1700E from 1900N to 1800N until 5/28/26 for curing prime coat. Road closed on 1820E from 1900N to 1600N until 6/2/26 for cement cure.  Road closed on 1600N from IL-130 to 1300E for laying dirt embankment. Road closed on 1400E from 1700N to 1500N for laying dirt embankment. Flagmen will be used for any short-term partial lane closures. Dirtworks will continue cleaning out culverts. Dunn Company will continue cement stabilization and pre pulverization. Evergreen will continue laying dirt embankment and hauling in rock to the Welcome Center. Thanks.