Coles Wind Road work for 5/26/26
No road work will be done during the holiday weekend.
Thank you all for putting up with us thus far the road work is nearing its end.
The following update is for Tuesday 5-26-26 it will be reposted Monday afternoon.
have a great weekend.
*No work over the weekend.
Road closed on 1700N from IL-130 to 2000E until 6/2/26 for cement stabilization and pre pulverization. Road closed on 1800N from IL-130 to 1950E until 5/28/26 for cement cure. Road closed on 1700E from 1900N to 1800N until 5/28/26 for curing prime coat. Road closed on 1820E from 1900N to 1600N until 6/2/26 for cement cure. Road closed on 1600N from IL-130 to 1300E for laying dirt embankment. Road closed on 1400E from 1700N to 1500N for laying dirt embankment. Flagmen will be used for any short-term partial lane closures.
Dirtworks will continue cleaning out culverts.
Dunn Company will continue cement stabilization and pre pulverization.
Evergreen will continue laying dirt embankment and hauling in rock to the Welcome Center.
Thanks.
Coles Wind Road work for 5/22/26
Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.Scheduled work subject to change due to weather/site conditions.
Road closed on 1700N from IL-130 to 2000E until 6/2/26 for cement stabilization and pre pulverization. Road closed on 1800N from IL-130 to 1950E until 5/28/26 for cement cure. Road closed on 1700E from 1900N to 1800N until 5/28/26 for spraying prime coat. Road closed on 1820E from 1900N to 1600N until 6/2/26 for cement cure. Flagmen will be used for any short-term partial lane closures.
Dirtworks will continue cleaning out culverts.
Dunn Company will continue cement stabilization and pre pulverization.
Evergreen will continue working on intersection 15 and adding rock to field entrances.
Thanks.
Coles Wind Road work for 5/21/26
Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.
Scheduled work subject to change due to weather/site conditions.
Road closure on 1820E from 1900N to 1700N until 5/28/26 for cement stabilization. Road closed on 1400E from 1700N to 1500N for laying A-1 oil and chip. Road closed on 1600N from IL-130 to 1300E for laying A-1 oil and chip. Road closed on 1800N from IL-130 to 1950E until 5/28/26 for cement cure. Road closed on 1700E from 1900N to 1800N until 6/2/26 for spraying prime coat. Road closed on 1700N from 1820E to 2000E until 6/2/26 for pre pulverization and cement stabilization. Flagmen will be used for any short-term partial lane closures.
Dirtworks will continue cleaning out culverts.
Dunn Company will continue cement stabilization and pre pulverization.
Evergreen will continue spraying prime coat, laying A-1 oil and chip, and hauling in rock to the Welcome Center.
Thanks,
Coles Wind Road work for 5/20/26
Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.Scheduled work subject to change due to weather/site conditions.
*OVERNIGHT Road closure on 1500N from IL-130 to 1500E for guardrail replacement. *OVERNIGHT Road closure on 1820E from 1900N to 1700N for cement stabilization. Road closed on 1400E from 1700N to 1500N for spraying prime coat. Road closed on 1600N from IL-130 to 1300E for spraying prime coat. Road closed on 1800N from IL-130 to 1950E for cement cure. Road closed on 1700E from 1900N to 1800N for laying 3” agg cap. Road closed on 1700N from 1820E to 2000E for pre pulverization. Flagmen will be used for any short-term partial lane closures.
Dirtworks will continue cleaning out culverts.
Dunn Company will continue cement stabilization and pre pulverization.
Evergreen will continue spraying prime coat, laying 3” agg cap, and hauling in rock to the Welcome Center.Thanks,
Coles Wind Road Work Update 5-19-26
Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.Scheduled work subject to change due to weather/site conditions.
Road closed on 1400E from 1700N to 1500N until 5/20/26 for spraying prime coat. Road closed on 1600N from IL-130 to 1300E until 5/20/26 for spraying prime coat. Road closed on 1800N from IL-130 to 1820E until 5/22/26 for pre pulverization and cement stabilization. Road closed on 1700E from 1900N to 1800N until 5/27/26 for cement cure. Road closed on 1820E from 1800N to 1700N until 5/27/26 for pre pulverization and cement stabilization. Road closed on 1700N from 1820E to 1900E for pre pulverization. Road closed on 1500N from IL-130 to 1500E for guardrail replacement. Road closed on 1500N from IL-130 to West street for laying add rock. Road closed on West Street from 1500N to 1400N for laying add rock. Road closed on 1400N from 1800E to 2000E for placing blister patches. Road closed on 1850E from 1400N to 1300N for placing blister patches. Flagmen will be used for any short-term partial lane closures.
Dirtworks will be cleaning out culverts.
Dunn Company will continue cement stabilization and pre pulverization.
Evergreen will continue spraying prime coat, laying add rock, placing blister patches, and hauling in rock to the Welcome Center.
Coles Wind Road Work Update 5-18-26
Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.Scheduled work subject to change due to weather/site conditions.
Road closed on 1400E from 1700N to 1500N until 5/19/26 for spraying prime coat. Road closed on 1600N from IL-130 to 1300E until 5/19/26 for spraying prime coat. Road closed on 1800N from IL-130 to 1820E until 5/20/26 for pre pulverization and cement stabilization. Road closed on 1700E from 1900N to 1800N until 5/20/26 for cement cure. Road closed on 1820E from 1800N to 1700N until 5/23/26 for pre pulverization and cement stabilization. Road closed on 1700N from 1820E to 1900E for pre pulverization. Road closed on 1500N from IL-130 to 1500E for guardrail replacement. Road closed on 1500N from IL-130 to West street for laying add rock. Road closed on West street from 1500N to 1400N for laying add rock. Road closed on 1400N from 1800E to 2000E for placing blister patches. Road closed on 1850E from 1400N to 1300N for placing blister patches. Flagmen will be used for any short-term partial lane closures.
Dirtworks will be cleaning out culverts.
Dunn Company will continue cement stabilization and pre pulverization.
Evergreen will continue spraying prime coat, laying add rock, placing blister patches, and hauling in rock to the Welcome Center.
Coles Wind Road Work Update 5-16-26 thru 5-17-26
All road work cancelled 5-15-26 thru 5-17-26 due to weather and site conditions
will update Sunday 5-17-26 for work to be performed on Monday 5-18-26
Coles Wind Road Work Update 5-15-26
Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.
Scheduled work subject to change due to weather/site conditions.
Road closed on 1400E from 1700N to 1400N until 5/15/26 for laying 3” agg cap. Road closed on 1600N from IL-130 to 1300E until 5/15/26 for laying 3” agg cap. Road closed on 1800N from IL-130 to 1820E until 5/20/26 for pre pulverization and cement stabilization. Road closed on 1700E from 1900N to 1800N until 5/20/26 for cement cure. Road closed on 1820E from 1800N to 1700N until 5/23/26 for pre pulverization and cement stabilization. Road closed on 1700N from 1820E to 1900E for pre pulverization. Flagmen will be used for any short-term partial lane closures.
Dirtworks will be cleaning out culverts.
Dunn Company will continue cement stabilization and pre pulverization.
Evergreen will continue laying 3” agg cap, spraying prime coat, and hauling in rock to the Welcome Center.
Coles Wind Road Work Update 5-14-26
Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.
Scheduled work subject to change due to weather/site conditions.
Road closed to thru traffic on 1500N from IL-130 to 1100E until 5/15/26. Road closed on 1400N from 1800E to 1850E for culvert extensions at A-17. Road closed on 1400E from 1700N to 1400N until 5/15/26 for laying 3” agg cap. Road closed on 1600N from IL-130 to 1300E until 5/15/26 for laying 3” agg cap. Road closed on 1800N from IL-130 to 1820E until 5/20/26 for pre pulverization and cement stabilization. Road closed on 1700E from 1900N to 1800N until 5/20/26 for cement cure. Road closed on 1820E from 1800N to 1700N for pre pulverization. Flagmen will be used for any short-term partial lane closures.
Dirtworks will continue installing pipe culverts.
Dunn Company will continue cement stabilization and pre pulverization.
Evergreen will continue laying 3” agg cap and hauling in rock to the Welcome Center.
Coles Wind Road Work Update 5-13-26
Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.
Scheduled work subject to change due to weather/site conditions.
Road closed to thru traffic on 1500N from IL-130 to 1100E until 5/15/26. Road closed on 1700N from IL-130 to 1300E for dirt embankment. Road closed on 1850E from 1400N to 1300N for culvert install A-18 and A-19. Road closed on 1400N from 1800E to 2000E for culvert install A-18 and A-19. Road closed on 1400E from 1800N to 1400N until 5/15/26 for laying 3” agg cap. Road closed on 1600N from IL-130 to 1300E until 5/15/26 for laying 3” agg cap. Road closed on 1800N from IL-130 to 1820E until 5/20/26 for pre pulverization and cement stabilization. Road closed on 1700E from 1900N to 1800N until 5/20/26 for pre pulverization and cement stabilization. Road closed on 1300E from 1800N to 1700N for dirt embankment. Flagmen will be used for any short-term partial lane closures while prepping for future culvert installs and ditch cleaning.
Dirtworks will continue installing pipe culverts.
Dunn Company will continue cement stabilization and pre pulverization.
Evergreen will continue laying 3” agg cap, dirt embankment, and hauling in rock to the Welcome Center.