Coles Wind Road work for 7/8/26

Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.

Will be granted access.

Scheduled work subject to change due to weather/site conditions.

Road closed on 1400N from 1300E to IL-130 until 7/9/26 for spraying prime coat and laying dirt embankment. Road closed on 1400E from 1600N to 1300N until 7/17/26 for cement cure. Road closed on 1500E from 1500N to 1200N until 7/9/26 for spraying prime coat. Road closed on 1300E from 1500N to 1400N for laying dirt embankment. Flagmen will be used for any short term road partial lane closures. 

Evergreen will continue laying dirt embankment and spraying prime coat.  Thanks,