Coles Wind Road work for 3/20/26
Road closed on 1600N from 1500E to 1400E for culvert install I-228 and C-61. Road closed on 1900N from IL-130 to 1400E for trenching and agg base widening. Road closed on 1800N from IL-130 to CR 1300E for trenching and agg base widening. Road closed on 1700N from IL-130 to 1300E for agg base widening. Road closed on 1400E from 1700N to 1400N for trenching. Road closed on 1300E from 1800N to 1700N for agg base widening. Flagmen will be used for any short-term partial lane closures while prepping for future culvert installs.
Dirtworks will continue trenching and installing culverts.
Evergreen continue agg base widening, prepping roads for widening, and hauling in rock to the Welcome Center.
Coles Wind Road work for 3/19/26
Road closed on 1500N from 1400E to 1300E for culvert install C-26. Road closed on 1600N from 1500E to 1400E for culvert install I-143. Road closed on 1900N from IL-130 to CR 1400E for agg base widening. Road closed on 1800N from IL-130 to 1300E for agg base widening. Road closed on 1700N from IL-130 to 1300E for trenching. Road closed on 1300E from 1800N to 1700N for trenching. Road closed on 1400E from 1700N to 1500N for trenching. Flagmen will be used for any short-term partial lane closures while prepping for future culvert installs.
Dirtworks will continue trenching and installing culverts.
Evergreen will start agg base widening, continue prepping roads for widening, and hauling in rock to the Welcome Center
Coles Wind Road work for 3/18/26
County Road 1500N from 1400E to 1300E will be closed overnight due to a field tile work.
Road Closed on 1500N from 1400E to 1300E for culvert install C-25, C-26, C-24. County Road 1800N will be closed from IL-130 going west 3 miles to 1300E for trenching. County Road 1900N will be closed from IL-130 to CR 1400E for trenching. County Road 1300E will be closed from 1800N south to 1700N for trenching. County Road 1700N will be closed from IL-130 to 1300E for trenching. Flagmen will be used for any short-term partial lane closures while prepping for future culvert installs.
Evergreen will continue to haul in rock to the Welcome Center for the aggregate stockpile. We will continue prepping CR 1700N, 1600N, 1500N, and 1400E for road widening
Coles Wind Road work for 3/17/26
All work subject to change due to weather and or site conditions
County Road 1500N will be closed from 1400E to 1300E for culvert installs. County Road 1800N will be closed from IL-130 going west 3 miles to 1300E for the road widening trench crew. Flagmen will be used for any short-term partial lane closures while prepping for future culvert installs.
Evergreen will continue hauling rock to the Welcome Center for the aggregate stockpile. We will continue prepping CR 1900N, 1700N, 1600N, and 1300E for road widening
Coles Wind Road work for 3/16/26
All work subject to change due to weather and or site conditions
County Road 1500N will be closed from 1500E to 1400E for culvert install C-29 and C-28. County Road 1800N will be closed from IL-130 going west 3 miles to 1300E for the road widening trench crew. Flagmen will be used for any short-term partial lane closures while prepping for future culvert installs on CR 1600N going west of IL-130.
Evergreen will continue hauling rock to the Welcome Center for the aggregate stockpile. We will continue prepping CR 1900N, 1700N, 1600N, and 1300E for road widening
Coles Wind Road work for 3/13/26
County Road 1500N will be closed from IL-130 going west 2 miles to 1400E to install pipe culvert C-31, C-30 and C-29. Flagmen will be used for any short term partial lane closures while prepping for future culvert installs on CR 1600N going west of IL-130.
Evergreen will continue to haul rock to the Welcome Center for the aggregate stockpile. We will continue prepping CR 1900N, 1800N, 1700N, and 1600N for road widening
Coles Wind Road work for 3/12/26
County Road 1500N will be closed from IL-130 going west 1 mile to CR 1500E to install pipe culvert C-32 and C-31. Flagmen will be used for a short-term partial lane closure on IL-130 to dump some backfill aggregate. Flagmen will also be used for any short-term partial lane closure on CR 1500N in between CR 1500E going west 2 miles to CR 1300E while prepping for future culvert work.
Evergreen will continue to haul rock into the Welcome Center for the aggregate stockpile. We will also continue to layout centerline offsets on CR 1900N, 1800N, and 1700N in preparation for road widening
Coles Wind Road work for 3/11/26
All work subject to change due to weather and or site conditions
Country Road 1500N will be closed from IL-130 going west 1 mile to CR 1500E to install pipe culvert C-32 and C-31. Flagmen will be used for a short-term partial lane closure on IL-130 to dump some backfill aggregate.
Crews will continue to haul rock into the Welcome Center for the aggregate stockpile. We will also continue to layout centerline offsets on CR 1900N, 1800N, and 1700N in preparation for road widening.
No Road closures today 3-5-26 due to weather / site conditions
No Road closures today 3-5-26 due to weather / site conditions
Coles Wind Road work for 3/10/26
County Road 1700N will be closed from 1400E to 1500E to install pipe culvert C-112 and C-113. A crew will also be on 1500N saw cutting and laying out pipe for Wednesday. Flagmen will be used for any short-term partial lane closures.
Crews will continue to haul in rock to the Welcome Cetner for the aggregate stockpile. We will start laying out centerline offsets in preparation for the road widening on CR 1900N, 1800N, and 1700N.