Coles Wind Road work for 3/19/26

Road closed on 1500N from 1400E to 1300E for culvert install C-26. Road closed on 1600N from 1500E to 1400E for culvert install I-143. Road closed on 1900N from IL-130 to CR 1400E for agg base widening. Road closed on 1800N from IL-130 to 1300E for agg base widening. Road closed on 1700N from IL-130 to 1300E for trenching.  Road closed on 1300E from 1800N to 1700N for trenching. Road closed on 1400E from 1700N to 1500N for trenching. Flagmen will be used for any short-term partial lane closures while prepping for future culvert installs.

Dirtworks will continue trenching and installing culverts.

Evergreen will start agg base widening, continue prepping roads for widening, and hauling in rock to the Welcome Center