Coles Wind Road work for 3/10/26

County Road 1700N will be closed from 1400E to 1500E to install pipe culvert C-112 and C-113. A crew will also be on 1500N saw cutting and laying out pipe for Wednesday. Flagmen will be used for any short-term partial lane closures.

Crews will continue to haul in rock to the Welcome Cetner for the aggregate stockpile. We will start laying out centerline offsets in preparation for the road widening on CR 1900N, 1800N, and 1700N.