Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.Will be granted access.Scheduled work subject to change due to weather/site conditions.Road closed on 1700N from IL-130 to 2000E until 6/2/26 for cement stabilization and pre pulverization. Road closed on 1800N from IL-130 to 1950E until 5/28/26 for cement cure. Road closed on 1700E from 1900N to 1800N until 5/28/26 for curing prime coat. Road closed on 1820E from 1900N to 1600N until 6/2/26 for cement cure. Road closed on 1600N from IL-130 to 1300E for laying dirt embankment. Road closed on 1400E from 1700N to 1500N for laying dirt embankment. Flagmen will be used for any short-term partial lane closures.Dirtworks will continue cleaning out culverts.Dunn Company will continue cement stabilization and pre pulverization.Evergreen will continue laying dirt embankment and hauling in rock to the Welcome Center.Thanks.