Coles Wind welcome center construction continues 2/23/2026
No weekend work. Monday: No work on public roads; stripping and grading at center.
February 20, 2026

No work Saturday 2-21-26 Sunday 2-22-26 Monday: 2-23-26No work on public roads. Evergreen will continue to strip topsoil, install entrance culverts, and haul in rock for the aggregate base at the Welcome Center.