Coles Wind Road Work Update 5-2-26
Chemical cure timelines close access across 1800N, 1300E, 1700N, and 1400E.
May 1, 2026

Busses and Local Residents within the road closures.Will be granted access.Scheduled work subject to change due to weather/site conditions.Road closed to thru traffic on 1500N from IL-130 to 1100E until 5/11/26. Road closed on 1800N from IL-130 to 1300E until 5/5/26 for prime coat. Road closed on 1300E from 1800N to 1700N until 5/5/26 for prime coat. Road closed on 1700N from IL-130 to 1300E until 5/8/26 for cement stabilization and cement cure. Road closed on 1400E from 1700N to 1600N until 5/13/26 for pre pulverization and cement stabilization.Dunn Company will continue cement stabilization.