Coles Wind Road work for 9/19/26
Clear weekend lanes. Monday box culvert installations block 1600N and 1700E rows.
September 18, 2026

Scheduled work subject to change due to weather/site conditionsTower components will continue arriving at the marshalling yard.No Road Closures over the weekend.Monday:Road closed on 1600N from 1500E to 1400E until 9/24/26 for box culvert install C-63.Dirtworks will continue installing the box culverts. Road closed on 1700E between 1800N and 1900N for crane crossing.