Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.Will be granted access.Scheduled work subject to change due to weather/site conditions.Road closed on 1700N from IL-130 to 2000E until 6/5/26 for placing blister patches and paving 3” cap rock. Road closed on 1820E from 1800N to 1600N until 6/8/26 for cement cure. Road closed on 1600N from IL-130 to 1875E until 6/8/26 for cement cure and cement stabilization. Road closed on 1800E from 1500N to 1600N until 6/8/26 for cement cure and cement stabilization. Road closed on 1850E from 1400N to 1300N until 6/12/26 for pre pulverization and cement stabilization. Road closed on 1400N from 1800E to 2000E until 6/12/26 for pre pulverization and cement stabilization. Flagmen will be used for any short-term partial lane closures.Dirtworks will continue cleaning culverts.Dunn Company will continue cement stabilization and pre pulverization.Evergreen will continue paving 3” cap rock and hauling rock to the Welcome Center.Thanks,