Coles Wind Road work for 5/22/26
Stabilization targets 1700N and 1820E; concrete curing limits 1800N routes.

Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.Will be granted access.Scheduled work subject to change due to weather/site conditions.Road closed on 1700N from IL-130 to 2000E until 6/2/26 for cement stabilization and pre pulverization. Road closed on 1800N from IL-130 to 1950E until 5/28/26 for cement cure. Road closed on 1700E from 1900N to 1800N until 5/28/26 for spraying prime coat. Road closed on 1820E from 1900N to 1600N until 6/2/26 for cement cure. Flagmen will be used for any short-term partial lane closures.Dirtworks will continue cleaning out culverts.Dunn Company will continue cement stabilization and pre pulverization.Evergreen will continue working on intersection 15 and adding rock to field entrances.Thanks.