Coles Wind Road work for 5/21/26
Large-scale oil/chip runs close corridors across 1400E, 1600N, and 1820E routes.

Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.Will be granted access.Scheduled work subject to change due to weather/site conditions.Road closure on 1820E from 1900N to 1700N until 5/28/26 for cement stabilization. Road closed on 1400E from 1700N to 1500N for laying A-1 oil and chip. Road closed on 1600N from IL-130 to 1300E for laying A-1 oil and chip. Road closed on 1800N from IL-130 to 1950E until 5/28/26 for cement cure. Road closed on 1700E from 1900N to 1800N until 6/2/26 for spraying prime coat. Road closed on 1700N from 1820E to 2000E until 6/2/26 for pre pulverization and cement stabilization. Flagmen will be used for any short-term partial lane closures.Dirtworks will continue cleaning out culverts.Dunn Company will continue cement stabilization and pre pulverization.Evergreen will continue spraying prime coat, laying A-1 oil and chip, and hauling in rock to the Welcome Center.Thanks,