Partial lane closure on 1800N from IL-130 to 1300E for grading ditches. Road closure on 1820E from 1700N to 1600N for placing a HMA patch at C-128. Road closure on 1600N from IL-130 to 1800E for repairing a crane crossing. Flaggers will be utilized for any short term partial lane closures.

Dirtworks will continue working on grading and Evergreen will continue installing HMA patches.

Tower components will continue arriving at the marshalling yard