Coles Wind Road Work Update 5-1-26

Busses and Local Residents within the road closures.

Will be granted access.

Scheduled work subject to change due to weather/site conditions.

Road closed to thru traffic on 1500N from IL-130 to 1100E until 5/11/26. Road closed on 1800N from IL-130 to 1300E until 5/5/26 for prime coat. Road closed on 1300E from 1800N to 1700N until 5/5/26 for prime coat. Road closed on 1700N from IL-130 to 1300E until 5/8/26 for cement stabilization and cement cure. Road closed on 1400N from 1800E to 2000E for agg base widening. Road closed on 1850E from 1400N to 1300N for agg base widening. Road closed on 1800N from 1700E to 1950E for culvert install A-10, A-8, and A-22. Road closed on 1400E from 1700N to 1500N until 5/13/26 for pre pulverization and cement stabilization. Road closed on 1600N from 1300E to 1400E for pre pulverization. Flagmen will be used for any short-term partial lane closures while prepping for future culvert installs. 

Dirtworks will continue installing pipe culverts. 

Dunn Company will continue cement stabilization and pre pulverization. 

Evergreen will continue agg base widening, spraying prime coat, and hauling in rock to the Welcome Center.