Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.
Scheduled work subject to change due to weather/site conditions.
Road closed on 1400E from 1700N to 1400N until 5/15/26 for laying 3” agg cap. Road closed on 1600N from IL-130 to 1300E until 5/15/26 for laying 3” agg cap. Road closed on 1800N from IL-130 to 1820E until 5/20/26 for pre pulverization and cement stabilization. Road closed on 1700E from 1900N to 1800N until 5/20/26 for cement cure. Road closed on 1820E from 1800N to 1700N until 5/23/26 for pre pulverization and cement stabilization. Road closed on 1700N from 1820E to 1900E for pre pulverization. Flagmen will be used for any short-term partial lane closures.
Dirtworks will be cleaning out culverts.
Dunn Company will continue cement stabilization and pre pulverization.
Evergreen will continue laying 3” agg cap, spraying prime coat, and hauling in rock to the Welcome Center.