Road closed to thru traffic on 1500N from IL-130 to 1100E starting on Monday 4/6/26 and reopening on Monday 4/27/26
Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.
Scheduled work subject to change due to weather/site conditions.
Road closed to thru traffic on 1500N from IL-130 to 1100E until 5/11/26. Road closed on 1900N from IL-130 to 1400E for 3” cap rock until 4/21/26. Road closed to thru traffic on 1800N from IL-130 to 1300E for cement stabilization and cure until 4/27/26. Road closed on 1400N from IL-130 to 1400E for culvert install A-1 and A-2. Road closed on 1700N from 1820E to 1900E for agg base widening. Road closed on 1500N from IL-130 to 1800E for agg base widening. Road closed on 1400N from 1800E to 2000E for trenching. Road closed on 1850E from 1400N to 1300N for trenching. Road closed on 1300E from 1800N to 1700N for pre pulverization. Flagmen will be used for any short-term partial lane closures while prepping for future culvert installs.
Dirtworks will continue trenching and installing culverts.
Dunn Company will continue cement stabilization and pre pulverization.
Evergreen will start laying cap rock, continue agg base widening, prepping roads for widening, and hauling in rock to the Welcome Center.