Coles Wind Road Work Update 4-15-26

Road closed to thru traffic on 1500N from IL-130 to 1100E starting on Monday 4/6/26 and reopening on Monday 4/27/26
Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.

Will be granted access.

Scheduled work subject to change due.

Road closed to thru traffic on 1500N from IL-130 to 1100E until 4/27/26. Road closed on 1700N from IL-130 to 1820E for culvert install I-205 and C-124. Road closed on 1300E from 1500N to 1400N for culvert install I-134. Road closed on 1900N from IL-130 to 1400E for cement stabilization. Road closed on 1800N from IL-130 to 1300E for pre pulverization. Road closed on 1900N from IL-130 to 1820E for agg base widening. Road closed on 1820E from 1800N to 1600N for trenching and agg base widening. Road closed on 1700N from IL-130 to 1900E for trenching and agg base widening. Flagmen will be used for any short-term partial lane closures while prepping for future culvert installs.

Dirtworks will continue trenching and installing culverts.

Dunn Company will continue cement stabilization and pre pulverization.

Evergreen will continue agg base widening, prepping roads for widening, and hauling in rock to the Welcome Center.

Thanks,