Coles Wind Road Work Update 4-11-26

Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.

Will be granted access.

Scheduled work subject to change due to weather/site conditions.

Road closed to thru traffic on 1500N from IL-130 to 1100E until 4/27/26. Road closed on 1800N from IL-130 to 1820E for trenching. Road closed on 1700N from IL-130 to 1700E for trenching. Road closed on 1700E from 1900N to 1800N for trenching.

Dirtworks will continue trenching.

Dunn Company will continue cement stabilization and pre pulverization.

Thanks,