Coles Wind Road work for 6/1/26

Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.

Will be granted access.

Scheduled work subject to change due to weather/site conditions.

Road closed on 1700N from IL-130 to 2000E until 6/5/26 for cement cure. Road closed on 1800N from IL-130 for laying dirt embankment. Road closed on 1700E from 1900N to 1800N for dirt embankment. Road closed on 1820E from 1900N to 1600N until 6/2/26 for cement cure and laying dirt embankment. Road closed on 1600N from IL-130 to 1875E until 6/8/26 for cement cure and cement stabilization. Road closed on 1800E from 1500N to 1600N until 6/8/26 for cement cure and cement stabilization. Road closed on 1850E from 1400N to 1300N for pre pulverization. Flagmen will be used for any short-term partial lane closures.

Dirtworks will continue cleaning culverts.

Dunn Company will continue cement stabilization and pre pulverization.

Evergreen will continue laying dirt embankment and hauling rock to the Welcome Center.

Thanks,