Coles Wind Road work for 6/18/26

Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.

Will be granted access.

Scheduled work subject to change due to weather/site conditions.

Tower Deliveries begin, please be patient with the increased traffic.

Road closed on 1300E from 1500N to 1375N until 6/22/26 for spraying prime coat. Road closed on 1400N from 1300E to IL-130 until 6/22/26 for cement stabilization and spraying prime coat. Road closed on 1400E from 1500N to 1300N until 6/22/26 for cement stabilization and cement cure. Road closed on 1500E from 1500N to 1200N until 6/22/26 for pre pulverization. Road closed on 1500N from IL-130 to 1800E until 6/19/26 for spraying prime coat. Road closed on 1700N from IL-130 to 2000E for laying dirt embankment. Road closed on 1820E from 1700N to 1600N for laying dirt embankment. Road closed on 1600N from IL-130 to 1820E for laying dirt embankment. Flagmen will be used for any short term road partial lane closures. 

Dirtworks will continue cleaning culverts.

Dunn Company will continue cement stabilization and pre pulverization.

Evergreen will continue working on field entrances and spraying prime coat.