Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.
Scheduled work subject to change due to weather/site conditions.
Road closed on 1300E from 1500N to 1375N until 6/22/26 for paving 3” cap rock. Road closed on 1400N from 1300E to IL-130 until 6/22/26 for cement stabilization and paving 3” cap rock. Road closed on 1400E from 1500N to 1300N until 6/22/26 for cement stabilization and cement cure. Road closed on 1500E from 1500N to 1200N until 6/22/26 for pre pulverization. Road closed on 1500N from IL-130 to 1800E until 6/19/26 for spraying prime coat. Flagmen will be used for any short-term road partial lane closures.
Dirtworks will continue cleaning culverts.
Dunn Company will continue cement stabilization and pre pulverization.
Evergreen will continue paving 3” cap rock.