Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.
Scheduled work subject to change due to weather/site conditions.
Road closed on 1300E from 1500N to 1400N until 6/22/26 for pre pulverization and cement stabilization. Road closed on 1820E from 1800N to 1600N until 6/13/26 for spraying prime coat and laying dirt embankment. Road closed on 1400N from 1800E to 2000E until 6/15/26 for spraying prime coat. Road closed on 1850E from 1400N to 1300N until 6/15/26 for spraying prime coat. Road closed on 1600N form IL-130 to 1875E until 6/13/26 for prime coat cure. Road closed on 1800E from 1600N to South Street/1400N until 6/19/26 for paving 3” cap rock. Road closed on 1500N from IL-130 to 1800E until 6/19/26 for cement cure and paving 3” cap rock. Road closed on 1770E from 1700N to 1300N until 6/15/26 for spraying prime coat. Road closed on 1700N from IL-130 to 2000E for laying dirt embankment. Road closed on 1400N from 1300E to 1500E for pre pulverization. Road closed on 1400E from 1500N to 1300N for pre pulverization. Road closed on 1375N from 1300E to 1270E until 6/22/26 for pre pulverization and cement stabilization. Flagmen will be used for any short-term partial lane closures.
Dirtworks will continue cleaning out culverts.
Dunn Company will continue cement stabilization and pre pulverization.
Evergreen will continue paving 3” cap rock, laying dirt embankment, and spraying prime coat.