Coles Wind Road work for 5/30/26

Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.

Will be granted access.

Scheduled work subject to change due to weather/site conditions.

Road closed on 1700N from IL-130 to 2000E until 6/5/26 for cement cure. Road closed on 1800N from IL-130 for laying oil and chip. Road closed on 1700E from 1900N to 1800N for laying oil and chip. Road closed on 1820E from 1900N to 1600N until 6/2/26 for cement cure and laying oil and chip. Road closed on 1600N from IL-130 to 1875E until 6/8/26 for pre pulverization and cement stabilization. Road closed on 1800E from 1500N to 1600N until 6/8/26 for pre pulverization and cement stabilization. Flagmen will be used for any short-term partial lane closures.

Dunn Company will continue cement stabilization and pre pulverization.

Evergreen will continue laying A-1 dust control oil and chip. Thanks.