Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.
Scheduled work subject to change due to weather/site conditions.
Road closed on 1700N from IL-130 to 2000E until 6/5/26 for cement stabilization and pre pulverization. Road closed on 1800N from IL-130 to 1950E until 5/30/26 for spraying prime coat. Road closed on 1700E from 1900N to 1800N until 5/30/26 for curing prime coat. Road closed on 1820E from 1900N to 1600N until 6/2/26 for cement stabilization and spraying prime coat. Road closed on 1600N from IL-130 to 1300E for laying dirt embankment. Road closed on 1400E from 1700N to 1500N for laying dirt embankment. Road closed on 1600N from IL-130 to 1875E until 6/8/26 for pre pulverization and cement stabilization. Road closed on 1800E from 1500N to 1600N until 6/8/26 for pre pulverization and cement stabilization. Flagmen will be used for any short-term partial lane closures.
Dirtworks will continue cleaning out culverts.
Dunn Company will continue cement stabilization and pre pulverization.
Evergreen will continue laying dirt embankment, spraying prime coat, and hauling in rock to the Welcome Center.

