Emergency Vehicles, Mail Carriers, School Busses and Local Residents within the road closures.
Will be granted access.
Scheduled work subject to change due to weather/site conditions.
Road closure on 1820E from 1900N to 1700N until 5/28/26 for cement stabilization. Road closed on 1400E from 1700N to 1500N for laying A-1 oil and chip. Road closed on 1600N from IL-130 to 1300E for laying A-1 oil and chip. Road closed on 1800N from IL-130 to 1950E until 5/28/26 for cement cure. Road closed on 1700E from 1900N to 1800N until 6/2/26 for spraying prime coat. Road closed on 1700N from 1820E to 2000E until 6/2/26 for pre pulverization and cement stabilization. Flagmen will be used for any short-term partial lane closures.
Dirtworks will continue cleaning out culverts.
Dunn Company will continue cement stabilization and pre pulverization.
Evergreen will continue spraying prime coat, laying A-1 oil and chip, and hauling in rock to the Welcome Center.