All scheduled work is subject to change due to weather / site conditions
Notice: Road closed to thru traffic on 1500N from IL-130 to 1100E starting on Monday 4/6/26 and reopening on Monday 4/27/26.
4-3-26
Road closed on 1500N from 1800E to 1700E for culvert install C-35 and I-141. Road closed on 1700N from IL-130 to 1500E for culvert install C-114. Road closed on 1700N from 1300E to 1400E for drainage correction at culvert C-107. Road closed on 1800N from 1300E to 1820E for laying dirt embankment and blister culvert patches. Road closed on 1600N from IL-130 to 1820E for trenching and agg base widening. Road closed on 1400N from IL-130 to 1300E for laying dirt embankment. Road closed on 1700N from 1400E to 1500E for laying blister culvert patches. Road closed on 1600N from IL-130 to 1300E to fill culvert crossings. Road closed on 1820E from 1600N to 1700N for trenching. Flagmen will be used for any short-term partial lane closures while prepping for future culvert installs.
Crews will continue trenching and installing culverts.
Crews will continue agg base widening, prepping roads for widening, and hauling in rock to the Welcome Center.