Road closed on 1700N from 1700E to 1820E for culvert install C-122. Road closed on 1700N from IL-130 to 1400E for culvert install C-110, C-114. Road closed on 1600N from 1300E to 1820E for placing dirt embankment. Road closed on 1500E from 1400N to 1200N for agg base widening. Road closed on 1400N from IL-130 to 1300E for agg base widening and trenching. Road closed on 1300E from 1500N to 1400N for trenching and agg base widening. Road closed on 1400E from 1700N to 1400N for placing dirt embankment. Road closed on 1800N from IL-130 to 1300E for 2” add rock. Flagmen will be used for any short-term partial lane closures while prepping for future culvert installs.
Dirtworks will continue trenching and installing culverts.
Evergreen will start laying 2” add rock, continue agg base widening, prepping roads for widening, and hauling in rock to the Welcome Center