Road closed on 1700N from IL-130 to 1820E for culvert install I-208, C-120, I-119, C-123. Road closed on 1300E from 1800N to 1700N for culvert install C-144. Road closed on 1700N from 1300E to 1400E for culvert install C-107 and C-108. Road closed on 1400E from 1700N to 1600N for agg base widening. Road closed on 1600N from IL-130 to 1300E for trenching. Road closed on 1600N from IL-130 to 1820E for agg base widening. Road closed on 1500E from 1400N to 1200N for agg base widening. Road closed on 1400N from IL-130 to 1300E for trenching. Road closed on 1800N from 1300E to 1500E for paving 2” Add Rock. Flagmen will be used for any short-term partial lane closures while prepping for future culvert installs.

 

crews will continue trenching and installing culverts.crews will continue agg base widening, prepping roads for widening, and hauling in rock to the Welcome Center.